Payment plan
Realiste’s Preliminary estimate based on date of handover
Mandatory municipal fee of 4% DLD does not count
We have alternative payment plans in this project. Contact our experts to get information
1
10% · 32 566 USD
At reservation · December 2025
Paid to the date: 10% · 32 566 USD
Remaining due payment: 293 097 USD
2
10% · 32 566 USD
March 2026
Paid to the date: 20% · 65 133 USD
Remaining due payment: 260 531 USD
3
5% · 16 283 USD
June 2026
Paid to the date: 25% · 81 416 USD
Remaining due payment: 244 248 USD
4
5% · 16 283 USD
September 2026
Paid to the date: 30% · 97 699 USD
Remaining due payment: 227 964 USD
5
70% · 227 964 USD
July 2028
Paid to the date: 100% · 325 663 USD
Remaining due payment: 0.0000 USD
Resale is available