Total:
70% - during construction
30% - after completion of construction (Over 30 Months)
Unit type:
Price:
Area: 782.0 sqft (72.65 sqm)
Views:
Payment plan:
Booking from the developer: 10%
Total:
70% - during construction
30% - after completion of construction (Over 30 Months)
Payment plan
Realiste’s Preliminary estimate based on date of handover
Mandatory municipal fee of 4% DLD does not count
1
10% · 32 677 USD
At reservation · July 2025
Paid to the date: 10% · 32 677 USD
Remaining due payment: 294 091 USD
2
8% · 26 141 USD
December 2025
Paid to the date: 18% · 58 818 USD
Remaining due payment: 267 950 USD
3
8% · 26 141 USD
May 2026
Paid to the date: 26% · 84 960 USD
Remaining due payment: 241 808 USD
Resale is available
4
8% · 26 141 USD
October 2026
Paid to the date: 34% · 111 101 USD
Remaining due payment: 215 667 USD
5
8% · 26 141 USD
March 2027
Paid to the date: 42% · 137 243 USD
Remaining due payment: 189 525 USD
6
8% · 26 141 USD
July 2027
Paid to the date: 50% · 163 384 USD
Remaining due payment: 163 384 USD
7
8% · 26 141 USD
December 2027
Paid to the date: 58% · 189 525 USD
Remaining due payment: 137 243 USD
8
12% · 39 212 USD
March 2028
Paid to the date: 70% · 228 738 USD
Remaining due payment: 98 030 USD
9
1% · 3 268 USD
May 2028
Paid to the date: 71% · 232 005 USD
Remaining due payment: 94 763 USD
10
1% · 3 268 USD
May 2028
Paid to the date: 72% · 235 273 USD
Remaining due payment: 91 495 USD
11
1% · 3 268 USD
July 2028
Paid to the date: 73% · 238 541 USD
Remaining due payment: 88 227 USD
12
1% · 3 268 USD
July 2028
Paid to the date: 74% · 241 808 USD
Remaining due payment: 84 960 USD
13
1% · 3 268 USD
August 2028
Paid to the date: 75% · 245 076 USD
Remaining due payment: 81 692 USD
14
1% · 3 268 USD
October 2028
Paid to the date: 76% · 248 344 USD
Remaining due payment: 78 424 USD
15
1% · 3 268 USD
October 2028
Paid to the date: 77% · 251 611 USD
Remaining due payment: 75 157 USD
16
1% · 3 268 USD
December 2028
Paid to the date: 78% · 254 879 USD
Remaining due payment: 71 889 USD
17
1% · 3 268 USD
December 2028
Paid to the date: 79% · 258 147 USD
Remaining due payment: 68 621 USD
18
1% · 3 268 USD
January 2029
Paid to the date: 80% · 261 414 USD
Remaining due payment: 65 354 USD
19
1% · 3 268 USD
March 2029
Paid to the date: 81% · 264 682 USD
Remaining due payment: 62 086 USD
20
1% · 3 268 USD
March 2029
Paid to the date: 82% · 267 950 USD
Remaining due payment: 58 818 USD
21
1% · 3 268 USD
May 2029
Paid to the date: 83% · 271 217 USD
Remaining due payment: 55 551 USD
22
1% · 3 268 USD
May 2029
Paid to the date: 84% · 274 485 USD
Remaining due payment: 52 283 USD
23
1% · 3 268 USD
July 2029
Paid to the date: 85% · 277 753 USD
Remaining due payment: 49 015 USD
24
1% · 3 268 USD
July 2029
Paid to the date: 86% · 281 020 USD
Remaining due payment: 45 748 USD
25
1% · 3 268 USD
August 2029
Paid to the date: 87% · 284 288 USD
Remaining due payment: 42 480 USD
26
1% · 3 268 USD
October 2029
Paid to the date: 88% · 287 556 USD
Remaining due payment: 39 212 USD
27
1% · 3 268 USD
October 2029
Paid to the date: 89% · 290 823 USD
Remaining due payment: 35 944 USD
28
1% · 3 268 USD
December 2029
Paid to the date: 90% · 294 091 USD
Remaining due payment: 32 677 USD
29
1% · 3 268 USD
December 2029
Paid to the date: 91% · 297 359 USD
Remaining due payment: 29 409 USD
30
1% · 3 268 USD
January 2030
Paid to the date: 92% · 300 627 USD
Remaining due payment: 26 141 USD
31
1% · 3 268 USD
March 2030
Paid to the date: 93% · 303 894 USD
Remaining due payment: 22 874 USD
32
1% · 3 268 USD
March 2030
Paid to the date: 94% · 307 162 USD
Remaining due payment: 19 606 USD
33
1% · 3 268 USD
May 2030
Paid to the date: 95% · 310 430 USD
Remaining due payment: 16 338 USD
34
1% · 3 268 USD
May 2030
Paid to the date: 96% · 313 697 USD
Remaining due payment: 13 071 USD
35
1% · 3 268 USD
July 2030
Paid to the date: 97% · 316 965 USD
Remaining due payment: 9 803 USD
36
1% · 3 268 USD
July 2030
Paid to the date: 98% · 320 233 USD
Remaining due payment: 6 535 USD
37
1% · 3 268 USD
August 2030
Paid to the date: 99% · 323 500 USD
Remaining due payment: 3 268 USD
38
1% · 3 268 USD
October 2030
Paid to the date: 100% · 326 768 USD
Remaining due payment: 0.0000 USD