Payment plan:
Booking from the developer: 20%

Total:
75% - during construction
25% - 25 months Post Handover

№2
Payment plan:
Booking from the developer: 20%

Total:
70% - during construction
30% - upon completion of construction
Payment plan

Realiste’s Preliminary estimate based on date of handover

Mandatory municipal fee of 4% DLD does not count

We have alternative payment plans in this project. Contact our experts to get information
1
20% · 86 413 USD
At reservation · July 2025
Paid to the date: 20% · 86 413 USD
Remaining due payment: 345 652 USD
2
1% · 4 321 USD
August 2025
Paid to the date: 21% · 90 734 USD
Remaining due payment: 341 331 USD
3
1% · 4 321 USD
September 2025
Paid to the date: 22% · 95 054 USD
Remaining due payment: 337 011 USD
4
1% · 4 321 USD
October 2025
Paid to the date: 23% · 99 375 USD
Remaining due payment: 332 690 USD
5
6% · 25 924 USD
November 2025
Paid to the date: 29% · 125 299 USD
Remaining due payment: 306 766 USD
6
1% · 4 321 USD
December 2025
Paid to the date: 30% · 129 620 USD
Remaining due payment: 302 446 USD
7
1% · 4 321 USD
January 2026
Paid to the date: 31% · 133 940 USD
Remaining due payment: 298 125 USD
8
1% · 4 321 USD
February 2026
Paid to the date: 32% · 138 261 USD
Remaining due payment: 293 804 USD
9
1% · 4 321 USD
March 2026
Paid to the date: 33% · 142 581 USD
Remaining due payment: 289 484 USD
10
1% · 4 321 USD
April 2026
Paid to the date: 34% · 146 902 USD
Remaining due payment: 285 163 USD
Resale is available
11
6% · 25 924 USD
May 2026
Paid to the date: 40% · 172 826 USD
Remaining due payment: 259 239 USD
12
1% · 4 321 USD
June 2026
Paid to the date: 41% · 177 147 USD
Remaining due payment: 254 918 USD
13
1% · 4 321 USD
July 2026
Paid to the date: 42% · 181 467 USD
Remaining due payment: 250 598 USD
14
1% · 4 321 USD
August 2026
Paid to the date: 43% · 185 788 USD
Remaining due payment: 246 277 USD
15
1% · 4 321 USD
September 2026
Paid to the date: 44% · 190 109 USD
Remaining due payment: 241 956 USD
16
1% · 4 321 USD
October 2026
Paid to the date: 45% · 194 429 USD
Remaining due payment: 237 636 USD
17
6% · 25 924 USD
November 2026
Paid to the date: 51% · 220 353 USD
Remaining due payment: 211 712 USD
18
1% · 4 321 USD
December 2026
Paid to the date: 52% · 224 674 USD
Remaining due payment: 207 391 USD
19
1% · 4 321 USD
January 2027
Paid to the date: 53% · 228 994 USD
Remaining due payment: 203 071 USD
20
1% · 4 321 USD
February 2027
Paid to the date: 54% · 233 315 USD
Remaining due payment: 198 750 USD
21
1% · 4 321 USD
March 2027
Paid to the date: 55% · 237 636 USD
Remaining due payment: 194 429 USD
22
1% · 4 321 USD
April 2027
Paid to the date: 56% · 241 956 USD
Remaining due payment: 190 109 USD
23
6% · 25 924 USD
May 2027
Paid to the date: 62% · 267 880 USD
Remaining due payment: 164 185 USD
24
1% · 4 321 USD
June 2027
Paid to the date: 63% · 272 201 USD
Remaining due payment: 159 864 USD
25
1% · 4 321 USD
July 2027
Paid to the date: 64% · 276 522 USD
Remaining due payment: 155 543 USD
26
1% · 4 321 USD
August 2027
Paid to the date: 65% · 280 842 USD
Remaining due payment: 151 223 USD
27
1% · 4 321 USD
September 2027
Paid to the date: 66% · 285 163 USD
Remaining due payment: 146 902 USD
28
1% · 4 321 USD
October 2027
Paid to the date: 67% · 289 484 USD
Remaining due payment: 142 581 USD
29
1% · 4 321 USD
November 2027
Paid to the date: 68% · 293 804 USD
Remaining due payment: 138 261 USD
30
1% · 4 321 USD
December 2027
Paid to the date: 69% · 298 125 USD
Remaining due payment: 133 940 USD
31
1% · 4 321 USD
January 2028
Paid to the date: 70% · 302 446 USD
Remaining due payment: 129 620 USD
32
5% · 21 603 USD
February 2028
Paid to the date: 75% · 324 049 USD
Remaining due payment: 108 016 USD
33
1% · 4 321 USD
March 2028
Paid to the date: 76% · 328 369 USD
Remaining due payment: 103 696 USD
34
1% · 4 321 USD
April 2028
Paid to the date: 77% · 332 690 USD
Remaining due payment: 99 375 USD
35
1% · 4 321 USD
May 2028
Paid to the date: 78% · 337 011 USD
Remaining due payment: 95 054 USD
36
1% · 4 321 USD
June 2028
Paid to the date: 79% · 341 331 USD
Remaining due payment: 90 734 USD
37
1% · 4 321 USD
July 2028
Paid to the date: 80% · 345 652 USD
Remaining due payment: 86 413 USD
38
1% · 4 321 USD
August 2028
Paid to the date: 81% · 349 973 USD
Remaining due payment: 82 092 USD
39
1% · 4 321 USD
September 2028
Paid to the date: 82% · 354 293 USD
Remaining due payment: 77 772 USD
40
1% · 4 321 USD
October 2028
Paid to the date: 83% · 358 614 USD
Remaining due payment: 73 451 USD
41
1% · 4 321 USD
November 2028
Paid to the date: 84% · 362 935 USD
Remaining due payment: 69 130 USD
42
1% · 4 321 USD
December 2028
Paid to the date: 85% · 367 255 USD
Remaining due payment: 64 810 USD
43
1% · 4 321 USD
January 2029
Paid to the date: 86% · 371 576 USD
Remaining due payment: 60 489 USD
44
1% · 4 321 USD
February 2029
Paid to the date: 87% · 375 897 USD
Remaining due payment: 56 168 USD
45
1% · 4 321 USD
March 2029
Paid to the date: 88% · 380 217 USD
Remaining due payment: 51 848 USD
46
1% · 4 321 USD
April 2029
Paid to the date: 89% · 384 538 USD
Remaining due payment: 47 527 USD
47
1% · 4 321 USD
May 2029
Paid to the date: 90% · 388 859 USD
Remaining due payment: 43 207 USD
48
1% · 4 321 USD
June 2029
Paid to the date: 91% · 393 179 USD
Remaining due payment: 38 886 USD
49
1% · 4 321 USD
July 2029
Paid to the date: 92% · 397 500 USD
Remaining due payment: 34 565 USD
50
1% · 4 321 USD
August 2029
Paid to the date: 93% · 401 820 USD
Remaining due payment: 30 245 USD
51
1% · 4 321 USD
September 2029
Paid to the date: 94% · 406 141 USD
Remaining due payment: 25 924 USD
52
1% · 4 321 USD
October 2029
Paid to the date: 95% · 410 462 USD
Remaining due payment: 21 603 USD
53
1% · 4 321 USD
November 2029
Paid to the date: 96% · 414 782 USD
Remaining due payment: 17 283 USD
54
1% · 4 321 USD
December 2029
Paid to the date: 97% · 419 103 USD
Remaining due payment: 12 962 USD
55
1% · 4 321 USD
January 2030
Paid to the date: 98% · 423 424 USD
Remaining due payment: 8 641 USD
56
1% · 4 321 USD
February 2030
Paid to the date: 99% · 427 744 USD
Remaining due payment: 4 321 USD
57
1% · 4 321 USD
March 2030
Paid to the date: 100% · 432 065 USD
Remaining due payment: 0.0000 USD

The information provided on this website is for informational purposes only. None of the content should be considered as investment advice or recommendations. Investing in real estate and other financial assets involves risks, and all investment decisions should be based on your own careful consideration and consultation with qualified professionals.

The administration of this website is not responsible for any losses or damages incurred as a result of using the information provided on the site. We recommend conducting your own research and analyzing the risks associated with any investment decisions. Past performance and results are not indicative of future outcomes. Investment results may vary based on individual circumstances, including financial situation and risk tolerance.

Any mention of specific investments or strategies is for illustrative and discussion purposes only and does not constitute a recommendation or endorsement. Such mentions do not necessarily reflect the views of the website administration.

We strongly advise consulting with a financial advisor or legal counsel before making any investment decisions. You are solely responsible for your investment actions and the risks associated with them.

By using this website, you agree that the website administration is not liable for any direct or indirect losses or damages resulting from the use of the information provided on the site.

Please exercise caution and care when making investment decisions.

Terms of Use