About
EX-d149eb561 - Canal Heights - Damac
Unit type:
Price:1050000.0 AED
Area: 408.0 sqft (37.9 sqm)
Views:
Payment plan:
Booking from the developer: 20%
Total:
80% - during construction
20% - upon completion of construction (Q2-2027)
Unit type:
Price:
Area: 408.0 sqft (37.9 sqm)
Views:
Payment plan:
Booking from the developer: 20%
Total:
80% - during construction
20% - upon completion of construction (Q2-2027)
Payment plan
Realiste’s Preliminary estimate based on date of handover
Mandatory municipal fee of 4% DLD does not count
We have alternative payment plans in this project. Contact our experts to get information
1
20% · 57 182 USD
At reservation · September 2025
Paid to the date: 20% · 57 182 USD
Remaining due payment: 228 727 USD
2
1% · 2 859 USD
October 2025
Paid to the date: 21% · 60 041 USD
Remaining due payment: 225 868 USD
3
1% · 2 859 USD
November 2025
Paid to the date: 22% · 62 900 USD
Remaining due payment: 223 009 USD
4
1% · 2 859 USD
December 2025
Paid to the date: 23% · 65 759 USD
Remaining due payment: 220 150 USD
5
6% · 17 155 USD
January 2026
Paid to the date: 29% · 82 913 USD
Remaining due payment: 202 995 USD
6
1% · 2 859 USD
February 2026
Paid to the date: 30% · 85 773 USD
Remaining due payment: 200 136 USD
7
1% · 2 859 USD
March 2026
Paid to the date: 31% · 88 632 USD
Remaining due payment: 197 277 USD
8
1% · 2 859 USD
April 2026
Paid to the date: 32% · 91 491 USD
Remaining due payment: 194 418 USD
9
1% · 2 859 USD
May 2026
Paid to the date: 33% · 94 350 USD
Remaining due payment: 191 559 USD
10
1% · 2 859 USD
June 2026
Paid to the date: 34% · 97 209 USD
Remaining due payment: 188 700 USD
11
1% · 2 859 USD
July 2026
Paid to the date: 35% · 100 068 USD
Remaining due payment: 185 841 USD
12
1% · 2 859 USD
August 2026
Paid to the date: 36% · 102 927 USD
Remaining due payment: 182 981 USD
Resale is available
13
6% · 17 155 USD
September 2026
Paid to the date: 42% · 120 082 USD
Remaining due payment: 165 827 USD
14
1% · 2 859 USD
October 2026
Paid to the date: 43% · 122 941 USD
Remaining due payment: 162 968 USD
15
1% · 2 859 USD
November 2026
Paid to the date: 44% · 125 800 USD
Remaining due payment: 160 109 USD
16
1% · 2 859 USD
December 2026
Paid to the date: 45% · 128 659 USD
Remaining due payment: 157 250 USD
17
1% · 2 859 USD
January 2027
Paid to the date: 46% · 131 518 USD
Remaining due payment: 154 391 USD
18
1% · 2 859 USD
February 2027
Paid to the date: 47% · 134 377 USD
Remaining due payment: 151 532 USD
19
1% · 2 859 USD
March 2027
Paid to the date: 48% · 137 236 USD
Remaining due payment: 148 672 USD
20
6% · 17 155 USD
April 2027
Paid to the date: 54% · 154 391 USD
Remaining due payment: 131 518 USD
21
1% · 2 859 USD
May 2027
Paid to the date: 55% · 157 250 USD
Remaining due payment: 128 659 USD
22
1% · 2 859 USD
June 2027
Paid to the date: 56% · 160 109 USD
Remaining due payment: 125 800 USD
23
1% · 2 859 USD
July 2027
Paid to the date: 57% · 162 968 USD
Remaining due payment: 122 941 USD
24
1% · 2 859 USD
August 2027
Paid to the date: 58% · 165 827 USD
Remaining due payment: 120 082 USD
25
6% · 17 155 USD
September 2027
Paid to the date: 64% · 182 981 USD
Remaining due payment: 102 927 USD
26
1% · 2 859 USD
October 2027
Paid to the date: 65% · 185 841 USD
Remaining due payment: 100 068 USD
27
1% · 2 859 USD
November 2027
Paid to the date: 66% · 188 700 USD
Remaining due payment: 97 209 USD
28
1% · 2 859 USD
December 2027
Paid to the date: 67% · 191 559 USD
Remaining due payment: 94 350 USD
29
1% · 2 859 USD
January 2028
Paid to the date: 68% · 194 418 USD
Remaining due payment: 91 491 USD
30
1% · 2 859 USD
February 2028
Paid to the date: 69% · 197 277 USD
Remaining due payment: 88 632 USD
31
6% · 17 155 USD
March 2028
Paid to the date: 75% · 214 431 USD
Remaining due payment: 71 477 USD
32
25% · 71 477 USD
April 2028
Paid to the date: 100% · 285 909 USD
Remaining due payment: 0.0000 USD