Payment plan
Realiste’s Preliminary estimate based on date of handover
Mandatory municipal fee of 4% DLD does not count
1
12% · 57 173 USD
At reservation · November 2025
Paid to the date: 12% · 57 173 USD
Remaining due payment: 419 272 USD
2
8% · 38 116 USD
December 2025
Paid to the date: 20% · 95 289 USD
Remaining due payment: 381 156 USD
3
8% · 38 116 USD
May 2026
Paid to the date: 28% · 133 405 USD
Remaining due payment: 343 041 USD
Resale is available
4
8% · 38 116 USD
November 2026
Paid to the date: 36% · 171 520 USD
Remaining due payment: 304 925 USD
5
8% · 38 116 USD
April 2027
Paid to the date: 44% · 209 636 USD
Remaining due payment: 266 809 USD
6
8% · 38 116 USD
October 2027
Paid to the date: 52% · 247 752 USD
Remaining due payment: 228 694 USD
7
8% · 38 116 USD
March 2028
Paid to the date: 60% · 285 867 USD
Remaining due payment: 190 578 USD
8
8% · 38 116 USD
August 2028
Paid to the date: 68% · 323 983 USD
Remaining due payment: 152 462 USD
9
8% · 38 116 USD
January 2029
Paid to the date: 76% · 362 098 USD
Remaining due payment: 114 347 USD
10
6% · 28 587 USD
February 2029
Paid to the date: 82% · 390 685 USD
Remaining due payment: 85 760 USD
11
6% · 28 587 USD
August 2029
Paid to the date: 88% · 419 272 USD
Remaining due payment: 57 173 USD
12
6% · 28 587 USD
February 2030
Paid to the date: 94% · 447 859 USD
Remaining due payment: 28 587 USD
13
6% · 28 587 USD
August 2030
Paid to the date: 100% · 476 445 USD
Remaining due payment: 0.0000 USD