About
EX-c8025349c - Mar Casa - Deyaar
Unit type:
Price:1650000.0 AED
Area: 760.0 sqft (70.61 sqm)
Views:
Payment plan:
Booking from the developer: 1%
Total:
76% - during construction
24% - after completion of construction (Q4-2026)
Unit type:
Price:
Area: 760.0 sqft (70.61 sqm)
Views:
Payment plan:
Booking from the developer: 1%
Total:
76% - during construction
24% - after completion of construction (Q4-2026)
Payment plan
Realiste’s Preliminary estimate based on date of handover
Mandatory municipal fee of 4% DLD does not count
1
12% · 53 914 USD
At reservation · July 2025
Paid to the date: 12% · 53 914 USD
Remaining due payment: 395 371 USD
2
8% · 35 943 USD
August 2025
Paid to the date: 20% · 89 857 USD
Remaining due payment: 359 428 USD
3
8% · 35 943 USD
January 2026
Paid to the date: 28% · 125 800 USD
Remaining due payment: 323 485 USD
Resale is available
4
8% · 35 943 USD
July 2026
Paid to the date: 36% · 161 743 USD
Remaining due payment: 287 542 USD
5
8% · 35 943 USD
December 2026
Paid to the date: 44% · 197 685 USD
Remaining due payment: 251 599 USD
6
8% · 35 943 USD
June 2027
Paid to the date: 52% · 233 628 USD
Remaining due payment: 215 657 USD
7
8% · 35 943 USD
November 2027
Paid to the date: 60% · 269 571 USD
Remaining due payment: 179 714 USD
8
8% · 35 943 USD
April 2028
Paid to the date: 68% · 305 514 USD
Remaining due payment: 143 771 USD
9
8% · 35 943 USD
September 2028
Paid to the date: 76% · 341 456 USD
Remaining due payment: 107 828 USD
10
6% · 26 957 USD
October 2028
Paid to the date: 82% · 368 413 USD
Remaining due payment: 80 871 USD
11
6% · 26 957 USD
April 2029
Paid to the date: 88% · 395 371 USD
Remaining due payment: 53 914 USD
12
6% · 26 957 USD
October 2029
Paid to the date: 94% · 422 328 USD
Remaining due payment: 26 957 USD
13
6% · 26 957 USD
April 2030
Paid to the date: 100% · 449 285 USD
Remaining due payment: 0.0000 USD