About
EX-d9310df06 - Mar Casa - Deyaar 
Unit type:
Price:899000.0 AED 
Area: 384.0 sqft (35.67 sqm)
Views:
Payment plan:
Booking from the developer: 1%
Total:
76% - during construction
24% - after completion of construction (Q4-2026)
Unit type:
Price:
Area: 384.0 sqft (35.67 sqm)
Views:
Payment plan:
Booking from the developer: 1%
Total:
76% - during construction
24% - after completion of construction (Q4-2026)
Payment plan
Realiste’s Preliminary estimate based on date of handover
Mandatory municipal fee of 4% DLD does not count
1
12% · 29 371 USD
At reservation · November 2025
Paid to the date: 12% · 29 371 USD
Remaining due payment: 215 386 USD
2
8% · 19 581 USD
December 2025
Paid to the date: 20% · 48 951 USD
Remaining due payment: 195 805 USD
3
8% · 19 581 USD
May 2026
Paid to the date: 28% · 68 532 USD
Remaining due payment: 176 225 USD
Resale is available
4
8% · 19 581 USD
November 2026
Paid to the date: 36% · 88 112 USD
Remaining due payment: 156 644 USD
5
8% · 19 581 USD
April 2027
Paid to the date: 44% · 107 693 USD
Remaining due payment: 137 064 USD
6
8% · 19 581 USD
October 2027
Paid to the date: 52% · 127 273 USD
Remaining due payment: 117 483 USD
7
8% · 19 581 USD
March 2028
Paid to the date: 60% · 146 854 USD
Remaining due payment: 97 903 USD
8
8% · 19 581 USD
August 2028
Paid to the date: 68% · 166 434 USD
Remaining due payment: 78 322 USD
9
8% · 19 581 USD
January 2029
Paid to the date: 76% · 186 015 USD
Remaining due payment: 58 742 USD
10
6% · 14 685 USD
February 2029
Paid to the date: 82% · 200 700 USD
Remaining due payment: 44 056 USD
11
6% · 14 685 USD
August 2029
Paid to the date: 88% · 215 386 USD
Remaining due payment: 29 371 USD
12
6% · 14 685 USD
February 2030
Paid to the date: 94% · 230 071 USD
Remaining due payment: 14 685 USD
13
6% · 14 685 USD
August 2030
Paid to the date: 100% · 244 756 USD
Remaining due payment: 0.0000 USD