112 - Arisha Terraces - QUBE Development
Unit type: 1
Price:1088000.0 AED
Area: 730.0 sqft (67.82 sqm)
Views:
Payment plan:
Booking from the developer: 10%
Total:
60% - during construction
40% - upon completion of construction
Unit type: 1
Price:
Area: 730.0 sqft (67.82 sqm)
Views:
Payment plan:
Booking from the developer: 10%
Total:
60% - during construction
40% - upon completion of construction
Payment plan
Realiste’s Preliminary estimate based on date of handover
Mandatory municipal fee of 4% DLD does not count
We have alternative payment plans in this project. Contact our experts to get information
1
10% · 29 621 USD
At reservation · August 2025
Paid to the date: 10% · 29 621 USD
Remaining due payment: 266 593 USD
2
5% · 14 811 USD
October 2025
Paid to the date: 15% · 44 432 USD
Remaining due payment: 251 783 USD
3
1% · 2 962 USD
November 2025
Paid to the date: 16% · 47 394 USD
Remaining due payment: 248 820 USD
4
1% · 2 962 USD
December 2025
Paid to the date: 17% · 50 357 USD
Remaining due payment: 245 858 USD
5
1% · 2 962 USD
January 2026
Paid to the date: 18% · 53 319 USD
Remaining due payment: 242 896 USD
6
1% · 2 962 USD
February 2026
Paid to the date: 19% · 56 281 USD
Remaining due payment: 239 934 USD
7
5% · 14 811 USD
March 2026
Paid to the date: 24% · 71 092 USD
Remaining due payment: 225 123 USD
8
1% · 2 962 USD
April 2026
Paid to the date: 25% · 74 054 USD
Remaining due payment: 222 161 USD
9
1% · 2 962 USD
May 2026
Paid to the date: 26% · 77 016 USD
Remaining due payment: 219 199 USD
10
1% · 2 962 USD
June 2026
Paid to the date: 27% · 79 978 USD
Remaining due payment: 216 237 USD
11
1% · 2 962 USD
July 2026
Paid to the date: 28% · 82 940 USD
Remaining due payment: 213 275 USD
12
5% · 14 811 USD
August 2026
Paid to the date: 33% · 97 751 USD
Remaining due payment: 198 464 USD
13
1% · 2 962 USD
September 2026
Paid to the date: 34% · 100 713 USD
Remaining due payment: 195 502 USD
14
1% · 2 962 USD
October 2026
Paid to the date: 35% · 103 675 USD
Remaining due payment: 192 540 USD
15
1% · 2 962 USD
November 2026
Paid to the date: 36% · 106 637 USD
Remaining due payment: 189 577 USD
16
1% · 2 962 USD
December 2026
Paid to the date: 37% · 109 599 USD
Remaining due payment: 186 615 USD
17
5% · 14 811 USD
January 2027
Paid to the date: 42% · 124 410 USD
Remaining due payment: 171 805 USD
18
1% · 2 962 USD
February 2027
Paid to the date: 43% · 127 372 USD
Remaining due payment: 168 842 USD
19
1% · 2 962 USD
March 2027
Paid to the date: 44% · 130 335 USD
Remaining due payment: 165 880 USD
20
1% · 2 962 USD
April 2027
Paid to the date: 45% · 133 297 USD
Remaining due payment: 162 918 USD
21
1% · 2 962 USD
May 2027
Paid to the date: 46% · 136 259 USD
Remaining due payment: 159 956 USD
22
5% · 14 811 USD
June 2027
Paid to the date: 51% · 151 070 USD
Remaining due payment: 145 145 USD
23
1% · 2 962 USD
July 2027
Paid to the date: 52% · 154 032 USD
Remaining due payment: 142 183 USD
24
1% · 2 962 USD
August 2027
Paid to the date: 53% · 156 994 USD
Remaining due payment: 139 221 USD
25
1% · 2 962 USD
September 2027
Paid to the date: 54% · 159 956 USD
Remaining due payment: 136 259 USD
26
1% · 2 962 USD
October 2027
Paid to the date: 55% · 162 918 USD
Remaining due payment: 133 297 USD
27
1% · 2 962 USD
November 2027
Paid to the date: 56% · 165 880 USD
Remaining due payment: 130 335 USD
28
1% · 2 962 USD
December 2027
Paid to the date: 57% · 168 842 USD
Remaining due payment: 127 372 USD
29
1% · 2 962 USD
January 2028
Paid to the date: 58% · 171 805 USD
Remaining due payment: 124 410 USD
30
1% · 2 962 USD
February 2028
Paid to the date: 59% · 174 767 USD
Remaining due payment: 121 448 USD
31
1% · 2 962 USD
March 2028
Paid to the date: 60% · 177 729 USD
Remaining due payment: 118 486 USD
32
40% · 118 486 USD
July 2028
Paid to the date: 100% · 296 215 USD
Remaining due payment: 0.0000 USD