Booking from the developer: 10%
Total:
60% - during construction
40% - upon completion of construction
Unit type:
Price:
Area: 782.0 sqft (72.65 sqm)
Views:
Payment plan:
Booking from the developer: 10%
Total:
60% - during construction
40% - upon completion of construction
Payment plan
Realiste’s Preliminary estimate based on date of handover
Mandatory municipal fee of 4% DLD does not count
We have alternative payment plans in this project. Contact our experts to get information
1
10% · 30 574 USD
At reservation · August 2025
Paid to the date: 10% · 30 574 USD
Remaining due payment: 275 167 USD
2
5% · 15 287 USD
October 2025
Paid to the date: 15% · 45 861 USD
Remaining due payment: 259 880 USD
3
1% · 3 057 USD
November 2025
Paid to the date: 16% · 48 919 USD
Remaining due payment: 256 823 USD
4
1% · 3 057 USD
December 2025
Paid to the date: 17% · 51 976 USD
Remaining due payment: 253 765 USD
5
1% · 3 057 USD
January 2026
Paid to the date: 18% · 55 033 USD
Remaining due payment: 250 708 USD
6
1% · 3 057 USD
February 2026
Paid to the date: 19% · 58 091 USD
Remaining due payment: 247 650 USD
7
5% · 15 287 USD
March 2026
Paid to the date: 24% · 73 378 USD
Remaining due payment: 232 363 USD
8
1% · 3 057 USD
April 2026
Paid to the date: 25% · 76 435 USD
Remaining due payment: 229 306 USD
9
1% · 3 057 USD
May 2026
Paid to the date: 26% · 79 493 USD
Remaining due payment: 226 248 USD
10
1% · 3 057 USD
June 2026
Paid to the date: 27% · 82 550 USD
Remaining due payment: 223 191 USD
11
1% · 3 057 USD
July 2026
Paid to the date: 28% · 85 608 USD
Remaining due payment: 220 134 USD
12
5% · 15 287 USD
August 2026
Paid to the date: 33% · 100 895 USD
Remaining due payment: 204 847 USD
13
1% · 3 057 USD
September 2026
Paid to the date: 34% · 103 952 USD
Remaining due payment: 201 789 USD
14
1% · 3 057 USD
October 2026
Paid to the date: 35% · 107 009 USD
Remaining due payment: 198 732 USD
15
1% · 3 057 USD
November 2026
Paid to the date: 36% · 110 067 USD
Remaining due payment: 195 674 USD
16
1% · 3 057 USD
December 2026
Paid to the date: 37% · 113 124 USD
Remaining due payment: 192 617 USD
17
5% · 15 287 USD
January 2027
Paid to the date: 42% · 128 411 USD
Remaining due payment: 177 330 USD
18
1% · 3 057 USD
February 2027
Paid to the date: 43% · 131 469 USD
Remaining due payment: 174 272 USD
19
1% · 3 057 USD
March 2027
Paid to the date: 44% · 134 526 USD
Remaining due payment: 171 215 USD
20
1% · 3 057 USD
April 2027
Paid to the date: 45% · 137 584 USD
Remaining due payment: 168 158 USD
21
1% · 3 057 USD
May 2027
Paid to the date: 46% · 140 641 USD
Remaining due payment: 165 100 USD
22
5% · 15 287 USD
June 2027
Paid to the date: 51% · 155 928 USD
Remaining due payment: 149 813 USD
23
1% · 3 057 USD
July 2027
Paid to the date: 52% · 158 985 USD
Remaining due payment: 146 756 USD
24
1% · 3 057 USD
August 2027
Paid to the date: 53% · 162 043 USD
Remaining due payment: 143 698 USD
25
1% · 3 057 USD
September 2027
Paid to the date: 54% · 165 100 USD
Remaining due payment: 140 641 USD
26
1% · 3 057 USD
October 2027
Paid to the date: 55% · 168 158 USD
Remaining due payment: 137 584 USD
27
1% · 3 057 USD
November 2027
Paid to the date: 56% · 171 215 USD
Remaining due payment: 134 526 USD
28
1% · 3 057 USD
December 2027
Paid to the date: 57% · 174 272 USD
Remaining due payment: 131 469 USD
29
1% · 3 057 USD
January 2028
Paid to the date: 58% · 177 330 USD
Remaining due payment: 128 411 USD
30
1% · 3 057 USD
February 2028
Paid to the date: 59% · 180 387 USD
Remaining due payment: 125 354 USD
31
1% · 3 057 USD
March 2028
Paid to the date: 60% · 183 445 USD
Remaining due payment: 122 296 USD
32
40% · 122 296 USD
July 2028
Paid to the date: 100% · 305 741 USD
Remaining due payment: 0.0000 USD