Total:
50% - during construction
50% - upon completion of construction (Q2-2026)
Unit type:
Price:
Area: 1084.0 sqft (100.71 sqm)
Views:
Payment plan:
Booking from the developer: 10%
Total:
50% - during construction
50% - upon completion of construction (Q2-2026)
Payment plan
Realiste’s Preliminary estimate based on date of handover
Mandatory municipal fee of 4% DLD does not count
1
10% · 46 154 USD
At reservation · December 2025
Paid to the date: 10% · 46 154 USD
Remaining due payment: 415 384 USD
2
10% · 46 154 USD
January 2026
Paid to the date: 20% · 92 308 USD
Remaining due payment: 369 230 USD
3
1% · 4 615 USD
February 2026
Paid to the date: 21% · 96 923 USD
Remaining due payment: 364 615 USD
4
1% · 4 615 USD
March 2026
Paid to the date: 22% · 101 538 USD
Remaining due payment: 360 000 USD
5
1% · 4 615 USD
April 2026
Paid to the date: 23% · 106 154 USD
Remaining due payment: 355 384 USD
6
1% · 4 615 USD
May 2026
Paid to the date: 24% · 110 769 USD
Remaining due payment: 350 769 USD
7
1% · 4 615 USD
June 2026
Paid to the date: 25% · 115 384 USD
Remaining due payment: 346 153 USD
8
1% · 4 615 USD
July 2026
Paid to the date: 26% · 120 000 USD
Remaining due payment: 341 538 USD
9
1% · 4 615 USD
August 2026
Paid to the date: 27% · 124 615 USD
Remaining due payment: 336 923 USD
10
1% · 4 615 USD
September 2026
Paid to the date: 28% · 129 231 USD
Remaining due payment: 332 307 USD
11
1% · 4 615 USD
October 2026
Paid to the date: 29% · 133 846 USD
Remaining due payment: 327 692 USD
12
1% · 4 615 USD
November 2026
Paid to the date: 30% · 138 461 USD
Remaining due payment: 323 077 USD
13
1% · 4 615 USD
December 2026
Paid to the date: 31% · 143 077 USD
Remaining due payment: 318 461 USD
14
1% · 4 615 USD
January 2027
Paid to the date: 32% · 147 692 USD
Remaining due payment: 313 846 USD
15
1% · 4 615 USD
February 2027
Paid to the date: 33% · 152 308 USD
Remaining due payment: 309 230 USD
16
1% · 4 615 USD
March 2027
Paid to the date: 34% · 156 923 USD
Remaining due payment: 304 615 USD
17
1% · 4 615 USD
April 2027
Paid to the date: 35% · 161 538 USD
Remaining due payment: 300 000 USD
18
1% · 4 615 USD
May 2027
Paid to the date: 36% · 166 154 USD
Remaining due payment: 295 384 USD
19
1% · 4 615 USD
June 2027
Paid to the date: 37% · 170 769 USD
Remaining due payment: 290 769 USD
20
1% · 4 615 USD
July 2027
Paid to the date: 38% · 175 384 USD
Remaining due payment: 286 154 USD
21
1% · 4 615 USD
August 2027
Paid to the date: 39% · 180 000 USD
Remaining due payment: 281 538 USD
22
1% · 4 615 USD
September 2027
Paid to the date: 40% · 184 615 USD
Remaining due payment: 276 923 USD
23
1% · 4 615 USD
October 2027
Paid to the date: 41% · 189 231 USD
Remaining due payment: 272 307 USD
24
1% · 4 615 USD
November 2027
Paid to the date: 42% · 193 846 USD
Remaining due payment: 267 692 USD
25
1% · 4 615 USD
December 2027
Paid to the date: 43% · 198 461 USD
Remaining due payment: 263 077 USD
26
1% · 4 615 USD
January 2028
Paid to the date: 44% · 203 077 USD
Remaining due payment: 258 461 USD
27
1% · 4 615 USD
February 2028
Paid to the date: 45% · 207 692 USD
Remaining due payment: 253 846 USD
28
1% · 4 615 USD
March 2028
Paid to the date: 46% · 212 307 USD
Remaining due payment: 249 231 USD
29
1% · 4 615 USD
April 2028
Paid to the date: 47% · 216 923 USD
Remaining due payment: 244 615 USD
30
1% · 4 615 USD
May 2028
Paid to the date: 48% · 221 538 USD
Remaining due payment: 240 000 USD
31
1% · 4 615 USD
June 2028
Paid to the date: 49% · 226 154 USD
Remaining due payment: 235 384 USD
32
1% · 4 615 USD
July 2028
Paid to the date: 50% · 230 769 USD
Remaining due payment: 230 769 USD
33
50% · 230 769 USD
August 2028
Paid to the date: 100% · 461 538 USD
Remaining due payment: 0.0000 USD