About
EX-e69cf68c5 - Lagoons (Marbella) - Damac
Unit type:
Price:1160000.0 AED
Area: 751.0 sqft (69.77 sqm)
Views:
Payment plan:
Booking from the developer: 20%
Total:
60% - during construction
40% - upon completion of construction (Q2-2026)
Unit type:
Price:
Area: 751.0 sqft (69.77 sqm)
Views:
Payment plan:
Booking from the developer: 20%
Total:
60% - during construction
40% - upon completion of construction (Q2-2026)
Payment plan
Realiste’s Preliminary estimate based on date of handover
Mandatory municipal fee of 4% DLD does not count
1
20% · 63 163 USD
At reservation · August 2025
Paid to the date: 20% · 63 163 USD
Remaining due payment: 252 651 USD
2
1% · 3 158 USD
October 2025
Paid to the date: 21% · 66 321 USD
Remaining due payment: 249 493 USD
3
1% · 3 158 USD
November 2025
Paid to the date: 22% · 69 479 USD
Remaining due payment: 246 334 USD
4
1% · 3 158 USD
December 2025
Paid to the date: 23% · 72 637 USD
Remaining due payment: 243 176 USD
5
1% · 3 158 USD
January 2026
Paid to the date: 24% · 75 795 USD
Remaining due payment: 240 018 USD
6
1% · 3 158 USD
March 2026
Paid to the date: 25% · 78 953 USD
Remaining due payment: 236 860 USD
Resale is available
7
5% · 15 791 USD
March 2026
Paid to the date: 30% · 94 744 USD
Remaining due payment: 221 069 USD
8
1% · 3 158 USD
April 2026
Paid to the date: 31% · 97 902 USD
Remaining due payment: 217 911 USD
9
1% · 3 158 USD
May 2026
Paid to the date: 32% · 101 060 USD
Remaining due payment: 214 753 USD
10
1% · 3 158 USD
June 2026
Paid to the date: 33% · 104 218 USD
Remaining due payment: 211 595 USD
11
1% · 3 158 USD
July 2026
Paid to the date: 34% · 107 377 USD
Remaining due payment: 208 437 USD
12
1% · 3 158 USD
August 2026
Paid to the date: 35% · 110 535 USD
Remaining due payment: 205 279 USD
13
1% · 3 158 USD
September 2026
Paid to the date: 36% · 113 693 USD
Remaining due payment: 202 121 USD
14
1% · 3 158 USD
October 2026
Paid to the date: 37% · 116 851 USD
Remaining due payment: 198 962 USD
15
5% · 15 791 USD
November 2026
Paid to the date: 42% · 132 642 USD
Remaining due payment: 183 172 USD
16
1% · 3 158 USD
December 2026
Paid to the date: 43% · 135 800 USD
Remaining due payment: 180 014 USD
17
1% · 3 158 USD
January 2027
Paid to the date: 44% · 138 958 USD
Remaining due payment: 176 856 USD
18
1% · 3 158 USD
March 2027
Paid to the date: 45% · 142 116 USD
Remaining due payment: 173 697 USD
19
1% · 3 158 USD
March 2027
Paid to the date: 46% · 145 274 USD
Remaining due payment: 170 539 USD
20
5% · 15 791 USD
April 2027
Paid to the date: 51% · 161 065 USD
Remaining due payment: 154 749 USD
21
1% · 3 158 USD
May 2027
Paid to the date: 52% · 164 223 USD
Remaining due payment: 151 590 USD
22
1% · 3 158 USD
June 2027
Paid to the date: 53% · 167 381 USD
Remaining due payment: 148 432 USD
23
1% · 3 158 USD
July 2027
Paid to the date: 54% · 170 539 USD
Remaining due payment: 145 274 USD
24
1% · 3 158 USD
August 2027
Paid to the date: 55% · 173 697 USD
Remaining due payment: 142 116 USD
25
5% · 15 791 USD
September 2027
Paid to the date: 60% · 189 488 USD
Remaining due payment: 126 325 USD
26
40% · 126 325 USD
November 2027
Paid to the date: 100% · 315 813 USD
Remaining due payment: 0.0000 USD