A-706 - Vivanti - Meteora Developers
Unit type: TYPE 03 | 1BHK
Price:1086000.0 AED
Area: 686.1 sqft (63.74 sqm)
Views: Boulevard
Payment plan:
Booking from the developer: 5%
Total:
60% - during construction
40% - after completion of construction
Unit type: TYPE 03 | 1BHK
Price:
Area: 686.1 sqft (63.74 sqm)
Views: Boulevard
Payment plan:
Booking from the developer: 5%
Total:
60% - during construction
40% - after completion of construction
Payment plan
Realiste’s Preliminary estimate based on date of handover
1
5% · 14 783 USD
At reservation · October 2025
Paid to the date: 5% · 14 783 USD
Remaining due payment: 280 886 USD
2
15% · 44 350 USD
November 2025
Paid to the date: 20% · 59 134 USD
Remaining due payment: 236 535 USD
3
10% · 29 567 USD
January 2026
Paid to the date: 30% · 88 701 USD
Remaining due payment: 206 968 USD
Resale is available
4
10% · 29 567 USD
July 2026
Paid to the date: 40% · 118 268 USD
Remaining due payment: 177 401 USD
5
10% · 29 567 USD
January 2027
Paid to the date: 50% · 147 835 USD
Remaining due payment: 147 835 USD
6
10% · 29 567 USD
May 2027
Paid to the date: 60% · 177 401 USD
Remaining due payment: 118 268 USD
7
1% · 2 957 USD
June 2027
Paid to the date: 61% · 180 358 USD
Remaining due payment: 115 311 USD
8
1% · 2 957 USD
July 2027
Paid to the date: 62% · 183 315 USD
Remaining due payment: 112 354 USD
9
1% · 2 957 USD
August 2027
Paid to the date: 63% · 186 272 USD
Remaining due payment: 109 398 USD
10
1% · 2 957 USD
September 2027
Paid to the date: 64% · 189 228 USD
Remaining due payment: 106 441 USD
11
1% · 2 957 USD
October 2027
Paid to the date: 65% · 192 185 USD
Remaining due payment: 103 484 USD
12
1% · 2 957 USD
November 2027
Paid to the date: 66% · 195 142 USD
Remaining due payment: 100 527 USD
13
1% · 2 957 USD
December 2027
Paid to the date: 67% · 198 098 USD
Remaining due payment: 97 571 USD
14
1% · 2 957 USD
January 2028
Paid to the date: 68% · 201 055 USD
Remaining due payment: 94 614 USD
15
1% · 2 957 USD
February 2028
Paid to the date: 69% · 204 012 USD
Remaining due payment: 91 657 USD
16
1% · 2 957 USD
March 2028
Paid to the date: 70% · 206 968 USD
Remaining due payment: 88 701 USD
17
1% · 2 957 USD
April 2028
Paid to the date: 71% · 209 925 USD
Remaining due payment: 85 744 USD
18
1% · 2 957 USD
May 2028
Paid to the date: 72% · 212 882 USD
Remaining due payment: 82 787 USD
19
1% · 2 957 USD
June 2028
Paid to the date: 73% · 215 838 USD
Remaining due payment: 79 831 USD
20
1% · 2 957 USD
July 2028
Paid to the date: 74% · 218 795 USD
Remaining due payment: 76 874 USD
21
1% · 2 957 USD
August 2028
Paid to the date: 75% · 221 752 USD
Remaining due payment: 73 917 USD
22
1% · 2 957 USD
September 2028
Paid to the date: 76% · 224 709 USD
Remaining due payment: 70 961 USD
23
1% · 2 957 USD
October 2028
Paid to the date: 77% · 227 665 USD
Remaining due payment: 68 004 USD
24
1% · 2 957 USD
November 2028
Paid to the date: 78% · 230 622 USD
Remaining due payment: 65 047 USD
25
1% · 2 957 USD
December 2028
Paid to the date: 79% · 233 579 USD
Remaining due payment: 62 091 USD
26
1% · 2 957 USD
January 2029
Paid to the date: 80% · 236 535 USD
Remaining due payment: 59 134 USD
27
1% · 2 957 USD
February 2029
Paid to the date: 81% · 239 492 USD
Remaining due payment: 56 177 USD
28
1% · 2 957 USD
March 2029
Paid to the date: 82% · 242 449 USD
Remaining due payment: 53 220 USD
29
1% · 2 957 USD
April 2029
Paid to the date: 83% · 245 405 USD
Remaining due payment: 50 264 USD
30
1% · 2 957 USD
May 2029
Paid to the date: 84% · 248 362 USD
Remaining due payment: 47 307 USD
31
1% · 2 957 USD
June 2029
Paid to the date: 85% · 251 319 USD
Remaining due payment: 44 350 USD
32
1% · 2 957 USD
July 2029
Paid to the date: 86% · 254 275 USD
Remaining due payment: 41 394 USD
33
1% · 2 957 USD
August 2029
Paid to the date: 87% · 257 232 USD
Remaining due payment: 38 437 USD
34
1% · 2 957 USD
September 2029
Paid to the date: 88% · 260 189 USD
Remaining due payment: 35 480 USD
35
1% · 2 957 USD
October 2029
Paid to the date: 89% · 263 146 USD
Remaining due payment: 32 524 USD
36
1% · 2 957 USD
November 2029
Paid to the date: 90% · 266 102 USD
Remaining due payment: 29 567 USD
37
1% · 2 957 USD
December 2029
Paid to the date: 91% · 269 059 USD
Remaining due payment: 26 610 USD
38
1% · 2 957 USD
January 2030
Paid to the date: 92% · 272 016 USD
Remaining due payment: 23 654 USD
39
1% · 2 957 USD
February 2030
Paid to the date: 93% · 274 972 USD
Remaining due payment: 20 697 USD
40
1% · 2 957 USD
March 2030
Paid to the date: 94% · 277 929 USD
Remaining due payment: 17 740 USD
41
1% · 2 957 USD
April 2030
Paid to the date: 95% · 280 886 USD
Remaining due payment: 14 783 USD
42
1% · 2 957 USD
May 2030
Paid to the date: 96% · 283 842 USD
Remaining due payment: 11 827 USD
43
1% · 2 957 USD
June 2030
Paid to the date: 97% · 286 799 USD
Remaining due payment: 8 870 USD
44
1% · 2 957 USD
July 2030
Paid to the date: 98% · 289 756 USD
Remaining due payment: 5 913 USD
45
1% · 2 957 USD
August 2030
Paid to the date: 99% · 292 712 USD
Remaining due payment: 2 957 USD
46
1% · 2 957 USD
September 2030
Paid to the date: 100% · 295 669 USD
Remaining due payment: 0.0000 USD