About
C-1308 - Vivanti - Meteora Developers
Unit type: TYPE 04 | 2BHK
Price:1455000.0 AED
Area: 33.56 sqft (3.12 sqm)
Views: Boulevard
Payment plan:
Booking from the developer: 5%
Total:
60% - during construction
40% - after completion of construction
Unit type: TYPE 04 | 2BHK
Price:
Area: 33.56 sqft (3.12 sqm)
Views: Boulevard
Payment plan:
Booking from the developer: 5%
Total:
60% - during construction
40% - after completion of construction
Payment plan
Realiste’s Preliminary estimate based on date of handover
1
5% · 19 809 USD
At reservation · June 2025
Paid to the date: 5% · 19 809 USD
Remaining due payment: 376 376 USD
2
15% · 59 428 USD
July 2025
Paid to the date: 20% · 79 237 USD
Remaining due payment: 316 949 USD
3
10% · 39 619 USD
September 2025
Paid to the date: 30% · 118 856 USD
Remaining due payment: 277 330 USD
Resale is available
4
10% · 39 619 USD
March 2026
Paid to the date: 40% · 158 474 USD
Remaining due payment: 237 711 USD
5
10% · 39 619 USD
September 2026
Paid to the date: 50% · 198 093 USD
Remaining due payment: 198 093 USD
6
10% · 39 619 USD
January 2027
Paid to the date: 60% · 237 711 USD
Remaining due payment: 158 474 USD
7
1% · 3 962 USD
February 2027
Paid to the date: 61% · 241 673 USD
Remaining due payment: 154 512 USD
8
1% · 3 962 USD
March 2027
Paid to the date: 62% · 245 635 USD
Remaining due payment: 150 551 USD
9
1% · 3 962 USD
April 2027
Paid to the date: 63% · 249 597 USD
Remaining due payment: 146 589 USD
10
1% · 3 962 USD
May 2027
Paid to the date: 64% · 253 559 USD
Remaining due payment: 142 627 USD
11
1% · 3 962 USD
June 2027
Paid to the date: 65% · 257 521 USD
Remaining due payment: 138 665 USD
12
1% · 3 962 USD
July 2027
Paid to the date: 66% · 261 483 USD
Remaining due payment: 134 703 USD
13
1% · 3 962 USD
August 2027
Paid to the date: 67% · 265 444 USD
Remaining due payment: 130 741 USD
14
1% · 3 962 USD
September 2027
Paid to the date: 68% · 269 406 USD
Remaining due payment: 126 779 USD
15
1% · 3 962 USD
October 2027
Paid to the date: 69% · 273 368 USD
Remaining due payment: 122 818 USD
16
1% · 3 962 USD
November 2027
Paid to the date: 70% · 277 330 USD
Remaining due payment: 118 856 USD
17
1% · 3 962 USD
December 2027
Paid to the date: 71% · 281 292 USD
Remaining due payment: 114 894 USD
18
1% · 3 962 USD
January 2028
Paid to the date: 72% · 285 254 USD
Remaining due payment: 110 932 USD
19
1% · 3 962 USD
February 2028
Paid to the date: 73% · 289 216 USD
Remaining due payment: 106 970 USD
20
1% · 3 962 USD
March 2028
Paid to the date: 74% · 293 177 USD
Remaining due payment: 103 008 USD
21
1% · 3 962 USD
April 2028
Paid to the date: 75% · 297 139 USD
Remaining due payment: 99 046 USD
22
1% · 3 962 USD
May 2028
Paid to the date: 76% · 301 101 USD
Remaining due payment: 95 085 USD
23
1% · 3 962 USD
June 2028
Paid to the date: 77% · 305 063 USD
Remaining due payment: 91 123 USD
24
1% · 3 962 USD
July 2028
Paid to the date: 78% · 309 025 USD
Remaining due payment: 87 161 USD
25
1% · 3 962 USD
August 2028
Paid to the date: 79% · 312 987 USD
Remaining due payment: 83 199 USD
26
1% · 3 962 USD
September 2028
Paid to the date: 80% · 316 949 USD
Remaining due payment: 79 237 USD
27
1% · 3 962 USD
October 2028
Paid to the date: 81% · 320 910 USD
Remaining due payment: 75 275 USD
28
1% · 3 962 USD
November 2028
Paid to the date: 82% · 324 872 USD
Remaining due payment: 71 313 USD
29
1% · 3 962 USD
December 2028
Paid to the date: 83% · 328 834 USD
Remaining due payment: 67 352 USD
30
1% · 3 962 USD
January 2029
Paid to the date: 84% · 332 796 USD
Remaining due payment: 63 390 USD
31
1% · 3 962 USD
February 2029
Paid to the date: 85% · 336 758 USD
Remaining due payment: 59 428 USD
32
1% · 3 962 USD
March 2029
Paid to the date: 86% · 340 720 USD
Remaining due payment: 55 466 USD
33
1% · 3 962 USD
April 2029
Paid to the date: 87% · 344 682 USD
Remaining due payment: 51 504 USD
34
1% · 3 962 USD
May 2029
Paid to the date: 88% · 348 643 USD
Remaining due payment: 47 542 USD
35
1% · 3 962 USD
June 2029
Paid to the date: 89% · 352 605 USD
Remaining due payment: 43 580 USD
36
1% · 3 962 USD
July 2029
Paid to the date: 90% · 356 567 USD
Remaining due payment: 39 619 USD
37
1% · 3 962 USD
August 2029
Paid to the date: 91% · 360 529 USD
Remaining due payment: 35 657 USD
38
1% · 3 962 USD
September 2029
Paid to the date: 92% · 364 491 USD
Remaining due payment: 31 695 USD
39
1% · 3 962 USD
October 2029
Paid to the date: 93% · 368 453 USD
Remaining due payment: 27 733 USD
40
1% · 3 962 USD
November 2029
Paid to the date: 94% · 372 415 USD
Remaining due payment: 23 771 USD
41
1% · 3 962 USD
December 2029
Paid to the date: 95% · 376 376 USD
Remaining due payment: 19 809 USD
42
1% · 3 962 USD
January 2030
Paid to the date: 96% · 380 338 USD
Remaining due payment: 15 847 USD
43
1% · 3 962 USD
February 2030
Paid to the date: 97% · 384 300 USD
Remaining due payment: 11 886 USD
44
1% · 3 962 USD
March 2030
Paid to the date: 98% · 388 262 USD
Remaining due payment: 7 924 USD
45
1% · 3 962 USD
April 2030
Paid to the date: 99% · 392 224 USD
Remaining due payment: 3 962 USD
46
1% · 3 962 USD
May 2030
Paid to the date: 100% · 396 186 USD
Remaining due payment: 0.0000 USD