About
C-209 - Vivanti - Meteora Developers
Unit type: TYPE 001 | 2 Bed + St
Price:1612000.0 AED
Area: 990.29 sqft (92.0 sqm)
Views: Corner boulevard
Payment plan:
Booking from the developer: 5%
Total:
60% - during construction
40% - after completion of construction
Unit type: TYPE 001 | 2 Bed + St
Price:
Area: 990.29 sqft (92.0 sqm)
Views: Corner boulevard
Payment plan:
Booking from the developer: 5%
Total:
60% - during construction
40% - after completion of construction
Payment plan
Realiste’s Preliminary estimate based on date of handover
1
5% · 21 944 USD
At reservation · May 2025
Paid to the date: 5% · 21 944 USD
Remaining due payment: 416 930 USD
2
15% · 65 831 USD
June 2025
Paid to the date: 20% · 87 775 USD
Remaining due payment: 351 099 USD
3
10% · 43 887 USD
August 2025
Paid to the date: 30% · 131 662 USD
Remaining due payment: 307 211 USD
Resale is available
4
10% · 43 887 USD
February 2026
Paid to the date: 40% · 175 549 USD
Remaining due payment: 263 324 USD
5
10% · 43 887 USD
August 2026
Paid to the date: 50% · 219 437 USD
Remaining due payment: 219 437 USD
6
10% · 43 887 USD
December 2026
Paid to the date: 60% · 263 324 USD
Remaining due payment: 175 549 USD
7
1% · 4 389 USD
January 2027
Paid to the date: 61% · 267 713 USD
Remaining due payment: 171 161 USD
8
1% · 4 389 USD
February 2027
Paid to the date: 62% · 272 101 USD
Remaining due payment: 166 772 USD
9
1% · 4 389 USD
March 2027
Paid to the date: 63% · 276 490 USD
Remaining due payment: 162 383 USD
10
1% · 4 389 USD
April 2027
Paid to the date: 64% · 280 879 USD
Remaining due payment: 157 994 USD
11
1% · 4 389 USD
May 2027
Paid to the date: 65% · 285 268 USD
Remaining due payment: 153 606 USD
12
1% · 4 389 USD
June 2027
Paid to the date: 66% · 289 656 USD
Remaining due payment: 149 217 USD
13
1% · 4 389 USD
July 2027
Paid to the date: 67% · 294 045 USD
Remaining due payment: 144 828 USD
14
1% · 4 389 USD
August 2027
Paid to the date: 68% · 298 434 USD
Remaining due payment: 140 439 USD
15
1% · 4 389 USD
September 2027
Paid to the date: 69% · 302 823 USD
Remaining due payment: 136 051 USD
16
1% · 4 389 USD
October 2027
Paid to the date: 70% · 307 211 USD
Remaining due payment: 131 662 USD
17
1% · 4 389 USD
November 2027
Paid to the date: 71% · 311 600 USD
Remaining due payment: 127 273 USD
18
1% · 4 389 USD
December 2027
Paid to the date: 72% · 315 989 USD
Remaining due payment: 122 885 USD
19
1% · 4 389 USD
January 2028
Paid to the date: 73% · 320 378 USD
Remaining due payment: 118 496 USD
20
1% · 4 389 USD
February 2028
Paid to the date: 74% · 324 766 USD
Remaining due payment: 114 107 USD
21
1% · 4 389 USD
March 2028
Paid to the date: 75% · 329 155 USD
Remaining due payment: 109 718 USD
22
1% · 4 389 USD
April 2028
Paid to the date: 76% · 333 544 USD
Remaining due payment: 105 330 USD
23
1% · 4 389 USD
May 2028
Paid to the date: 77% · 337 932 USD
Remaining due payment: 100 941 USD
24
1% · 4 389 USD
June 2028
Paid to the date: 78% · 342 321 USD
Remaining due payment: 96 552 USD
25
1% · 4 389 USD
July 2028
Paid to the date: 79% · 346 710 USD
Remaining due payment: 92 163 USD
26
1% · 4 389 USD
August 2028
Paid to the date: 80% · 351 099 USD
Remaining due payment: 87 775 USD
27
1% · 4 389 USD
September 2028
Paid to the date: 81% · 355 487 USD
Remaining due payment: 83 386 USD
28
1% · 4 389 USD
October 2028
Paid to the date: 82% · 359 876 USD
Remaining due payment: 78 997 USD
29
1% · 4 389 USD
November 2028
Paid to the date: 83% · 364 265 USD
Remaining due payment: 74 608 USD
30
1% · 4 389 USD
December 2028
Paid to the date: 84% · 368 654 USD
Remaining due payment: 70 220 USD
31
1% · 4 389 USD
January 2029
Paid to the date: 85% · 373 042 USD
Remaining due payment: 65 831 USD
32
1% · 4 389 USD
February 2029
Paid to the date: 86% · 377 431 USD
Remaining due payment: 61 442 USD
33
1% · 4 389 USD
March 2029
Paid to the date: 87% · 381 820 USD
Remaining due payment: 57 054 USD
34
1% · 4 389 USD
April 2029
Paid to the date: 88% · 386 208 USD
Remaining due payment: 52 665 USD
35
1% · 4 389 USD
May 2029
Paid to the date: 89% · 390 597 USD
Remaining due payment: 48 276 USD
36
1% · 4 389 USD
June 2029
Paid to the date: 90% · 394 986 USD
Remaining due payment: 43 887 USD
37
1% · 4 389 USD
July 2029
Paid to the date: 91% · 399 375 USD
Remaining due payment: 39 499 USD
38
1% · 4 389 USD
August 2029
Paid to the date: 92% · 403 763 USD
Remaining due payment: 35 110 USD
39
1% · 4 389 USD
September 2029
Paid to the date: 93% · 408 152 USD
Remaining due payment: 30 721 USD
40
1% · 4 389 USD
October 2029
Paid to the date: 94% · 412 541 USD
Remaining due payment: 26 332 USD
41
1% · 4 389 USD
November 2029
Paid to the date: 95% · 416 930 USD
Remaining due payment: 21 944 USD
42
1% · 4 389 USD
December 2029
Paid to the date: 96% · 421 318 USD
Remaining due payment: 17 555 USD
43
1% · 4 389 USD
January 2030
Paid to the date: 97% · 425 707 USD
Remaining due payment: 13 166 USD
44
1% · 4 389 USD
February 2030
Paid to the date: 98% · 430 096 USD
Remaining due payment: 8 777 USD
45
1% · 4 389 USD
March 2030
Paid to the date: 99% · 434 485 USD
Remaining due payment: 4 389 USD
46
1% · 4 389 USD
April 2030
Paid to the date: 100% · 438 873 USD
Remaining due payment: 0.0000 USD